1. The level at which the project is managed is generally called
a. Top Level
b. Initial Level
c. Work package Level (Lesson no 22 Page no 153 Handouts)
d. Secondary Level
2. Which of the following phases can also be referred to as the design phase? (Doubtful)
a. Concept phase
b. Development phase
c. Implementation phase
d. Acquisition phase
3. Which of the following is a product-oriented family tree subdivision of the hardware, services, and data required to produce the end product?
a. Statement of work (SOW)
b. Project Specifications
c. Milestone schedule
d. Work breakdown Structure (WBS) (Lesson no 22 Page no 151 Handouts)
4. Which of the following is involved in economic feasibility?
a. Benefit-cost analysis
b. Breakeven analysis
c. Tangible and intangible aspects
d. All of the given options (Lesson no 8 Page no 70 Handouts)
5. For projects internal to the company, the Statement of Work (SOW) is prepared by which of the following?
a. Contractor
b. Line Manager
c. Functional Manager
d. Project Office (Lesson no 21 Page no 147 Handouts)
6. A Gantt chart is useful in determining _____________. (Doubtful)
a. The level of effort for a task.
b. When a task starts and stops.
c. Which are the critical tasks.
d. Who is assigned to do a task
7. Which of the following is the ability to work with people, making a cooperative effort, do teamwork, make them feel secure and free to express their opinions?
a. Technical Skill
b. Human skill (Lesson no 3 Page no 19 Handouts)
c. Conceptual skill
d. Design skill
8. To be effective as a project manager, an individual must have: (Doubtful)
a. Management skills
b. Technical skills
c. Leadership skills
d. All of the given options
Note: Focus on the underline word individual.
9. Which of the following statements gives the definition of a Project Plan?
a. Working out of sub-components in some degree of detail
b. To cover areas of government legislation & regulation related to “use of resources”
c. “Planned use of any /all resources”. A succession of five-year plans
d. A structured sequence of events leading to the desired set of objectives.
10. Which of the following is designed to provide an overview of the primary issues related to a business idea?
a. Project Plan
b. Scope statement
c. Feasibility Study (Lesson no 9 Page no 73 Handouts)
d. Work Breakdown Structure
11. In which of the following phases, the project’s scope, and objectives are determined?
a. Conceptual
b. Development
c. Implementation
d. Close-out (Not Sure)
12. Which of the following is a process to determine the viability of a project, and provides a framework and direction for its development and delivery? (Doubtful)
a. Project Plan
b. Scope statement
c. Feasibility Study
d. Work Breakdown Structure
13. Which of the following is the objective of the kick-off meeting?
a. Establishing working relationships within the team
b. Setting goals and objectives for the team
c. Identifying project problem areas
d. All of the given options
14. Which of the following is what the system does and includes system design, reliability, quality, maintainability, and reparability?
a. Performance (Lesson no 17 Page no 132 Handouts)
b. Effectiveness
c. Constraints
d. Strategies
15. After Initial feasibility analysis, the next step is to prepare: (Doubtful)
a. Project Plan Correct
b. Scope statement
c. System Proposal
d. Work Breakdown Structure
16. Which of the following involves motivation, disciplining, managing conflict, staffing, and training?
a. Traditional Management
b. Communication
c. Human Resource Management (Lesson no 3 Page no 18 Handouts)
d. Networking
17. Which of the following should not be conducted as a forum merely to support a desire that the project will be successful?
a. Project Plan
b. Scope statement
c. Feasibility Study (Lesson no 9 Page no 75 Handouts)
d. Work Breakdown Structure
18. Fredrick Taylor’s major concerns were all of the following, EXCEPT:
a. To increase efficiency in production
b. To decrease cost
c. To raise profits through higher productivity
d. To decrease the salaries of the workers (Lesson no 1 Page no 1 Handouts)
19. Which of the following statements gives the Technical definition of
Project Planning?
a. Working out of sub-components in some degree of detail
b. To cover areas of government legislation & regulation related to “use of resources”
c. “Planned use of any /all resources”- Succession of five-year plans
d. Structured sequence of events leading to the desired set of objectives
20. All of the following are internal operating variables for strategic planning in the tire industry EXCEPT:
a. Product Changes
b. Research & Development
c. Volume (Economies of Scale)
d. Capacity of Plants (Lesson no 20 Page no 143 Handouts)
21. All of the following are life cycle phases used in engineering EXCEPT:
a. Start-up
b. Definition
c. Formation (Lesson no 20 Page no 144 Handouts)
d. Termination
22. Which of the following includes the preliminary evaluation of an idea?
a. Conceptual Phase (Lesson no 5 Page no 37 Handouts)
b. Planning Phase
c. Testing Phase
d. Implementation Phase
23. The best way to control creeping scope is with a good definition of which of the following?
a. Specifications
b. Requirements (Lesson no 21 Page no 148 Handouts)
c. Milestones
d. Statement of Work (SOW)
24. The Kala Bagh Dam project could not be started because it was not feasible ______. (Doubtful)
a. Politically
b. Legally
c. Economically
d. Socially
25. Which of the following life cycle phases is also called “defining the requirements”?
a. Conceptualization
b. Feasibility
c. Preliminary planning (Lesson no 20 Page no 145 Handouts)
d. Detail planning
26.Which of the following activities is performed by the Project Administration Manager? (Doubtful)
a. Office Services
b. Contract Plan
c. Expediting
d. Inspection
27. Which of the following refers to “a specification of series of actions, acts or operations, which have to be executed in the same manner in order to always obtain the same result in the same circumstances”? (Doubtful)
a. Policy
b. *Procedure (Lecture no 18 Page no 139 Handouts)
c. Standard
d. Decision
28. Which of the following statements is TRUE for Work breakdown Structure (WBS)? (Doubtful)
a. Project Manager must structure work into small elements that are manageable
b. Project Manager must structure work into small elements that are independent
c. Project Manager must structure work into small elements that are measurable
29. All of the following are life cycle phases used in construction EXCEPT:
a. Data gathering and procedures
b. Construction
c. Testing
d. Implementation (Lesson no 20 Page no 144 Handouts)
30. Which of the following information is required for a plan of execution?
a. Scope of work to be performed
b. Preliminary Cost Estimates
c. Site Visitation Report
d. All of the given options (lesson no 15 Page no 121 Handouts)