1) Dummy activity is represented by ____.

Select the correct option

a) doted line

b) doted line with right to left arrow

c) doted line with left to right arrow

d) left to right arrow


2) In Project Management. Critical path method is based on ___ times.

Select the correct option

a) deterministic

b) probabilistic

c) stochastic

d) serial


3) Which of the following is an operations research (OR) process? 

Select the correct option

a) Linear Programming

b) Networking

c) Observation

d) Simplex method


4) CPM is abbreviation of 

Select the correct option

a) Constant Process Method

b) Critical Path Method

c) Continuous Path Membership

d) Critical Performance Method


5) In a network flow diagram, a/an ___ is shown by dotted arrows and these consume no time or resources.

Select the correct option

a) activity

b) branch

c) dummy

d) nodes


6) In a project, a network diagrams shows the ___ relations of the inter related activities along with their corresponding activity times.

Select the correct option

a) deterministic and probabilistic

b) precedence or succession

c) union and intersection

d) dummy and artificial


7) Which of the following is not a problem of probabilistic technique.

Select the correct option

a) Linear programming

b) Decision analysis

c) Game theory

d) Forecasting


8) In a network flow diagram, the precedence relationship among the activities are indicated through ___.

Select the correct option

a) project

b) branch

c) dummy

d) nodes


8) Operations research (OR) is the application of quantitative methods to ___ making.

Select the correct option

a) formula

b) decision

c) observation

d) all of these


9) In a network flow diagram, if an activity (i,j) starts earlier

after two days and finish earlier on fifth day, then which of the following will be its completion time?

Select the correct option

a) Three days

b) Five days

c) Two days

d) Ten days


10) Duration of the project is described by the ___ to complete the project.

Select the correct option

a) shortest time

b) longest time

c) latest start time

d) quick time


11) Which of the following is not a categories of the operations research (OR) techniques.

Select the correct option

a) Linear mathematical programming technique

b) Feasible solution

c) Inventory techniques

d) Network techniques


12) In 1958, Saaty defined OR as “The art of giving ___ answer to problems to which otherwise, ___ answers are given.”

Select the correct option

a) bad, worse

b) worse, bad

c) good, excellent

d) excellent, worse


13) PERT is an acronym for ___.

Select the correct option

a) Program Evaluation and Review Technique

b) Performance Evaluation and Review Technique Observation

c) Program Execution and Revenue Technique

d) Program Evaluation and Review Teacher


14) Operations research is based on ___.

Select the correct option

a) engineering

b) economics

c) computing

d) all of these


15) In the phase of Early Start and Early Finish, to find the Critical Path in a network flow diagram, the computations are proceeded from ___ to the final event.

Select the correct option

a) bottom to top

b) right to left

c) left to right

d) top to bottom