1. The more you refine the task, the more you can:
a) Estimate task with accuracy
b) Conclude about scope with accuracy
c) Schedule the project with accuracy
d) All of the given options
2. The boundary times defines the following parameter(s) for a project:
a) The latest time for task initiation before the minimum project completion time is delayed
b) The earliest finish
c) The latest finish
d) All of the given option
3. Schedule Performance Index (SPI) is equal to
a) BCWP / BCWS
b) BCWP * BCWS
c) BCWP + BCWS
d) BCWP – BCWS
4. MTTF is the abbreviation of
a) Median tie to failure
b) Mean time to failure
c) Mean time to forward
d) Moderate time to failure
See Also:
Solved CS605 Midterm Past Papers by Moaaz with Reference Answer
5. Earned Value Analysis (EVA) is a ___ technique for assessing the progress of a project.
a) Qualitative
b) Quantitative
c) Subjective
d) None of the given options
6. Defining a “Task Network” helps in defining:
a) Cost of the project
b) The resources required for project
c) Third party tools required for project
d) Sequence in which activities will be performed
7. BAC stand for
a) Budgeted Analysis Cost
b) Budget and cost
c) Budget at compilation
d) Budget at Completion
8. Following are effective guidelines for Review EXCEPT
a) We need to review the product not the producer
b) Be sensitive to personal egos
c) Errors should be pointed out
d) Tone should be high and strict
9. ___ is one of the techniques used during severe deadline pressure.
a) PERT
b) CPM
c) Time Boxing
d) Macroscopic scheduling
10. FTR stands for
a) Feasibility of technical requirement
b) Fetched Technical Requirement
c) Formal Technical Review
d) None of the given options